Progress claims (progress billing) explained, with a template
A progress claim is a request for payment for the part of a job finished so far, measured against the agreed price. Here's how progress claims (progress billing) work, how to calculate each one, a template you can copy, a worked example, and where the rules sit in Australia, New Zealand, the UK, the US and Canada.
A progress claim is a request for payment for the work completed on a job so far, worked out as a share of the agreed contract price. Instead of one invoice at the end, you bill in stages as the job moves, so the money arrives while you are still paying for labour and materials.
Different markets use different names. Progress claims (progress billing) are also called progress payment claims, payment claims or, on many US commercial jobs, payment applications. The idea is the same everywhere: agree how the job will be billed before you start, then claim what has been done at each point.
What is a progress claim?
A progress claim is an interim bill on a job that runs over weeks or months. Each claim states the value of the work done to date, subtracts what has already been claimed, and asks for the difference.
It suits any trade business doing larger work: renovations, fit-outs, new builds, commercial maintenance contracts, or anything where waiting until the end would leave you carrying the cost for a month or more. It is agreed in the quote (or estimate) or contract, so the customer knows the stages before work starts.
Progress claim, invoice or deposit?
| Deposit | Progress claim | Final invoice | |
|---|---|---|---|
| When | Before work starts | During the job, at stages or monthly | When the job is complete |
| Based on | An agreed amount or % | Work done to date | Whatever has not yet been billed |
| Purpose | Commitment, materials | Cash flow during the job | Closing the job |
| Typical jobs | Most jobs with ordered materials | Jobs running weeks or months | Every job |
How do you calculate a progress claim?
Calculate a progress claim as the value of work done to date, minus everything already claimed, minus any agreed holdback, plus tax. The value of work done to date can be measured in one of three ways, and the contract should say which.
- By stage (milestones): the price is split into stages such as rough-in, lock-up and fit-off, and each stage is claimed in full when it is finished.
- By percentage complete: the job is broken into line items, and each line is claimed at the percentage finished. US commercial work calls this list a schedule of values.
- By fixed amount: an agreed dollar amount is claimed at set dates, such as each month, with the balance on completion.
Whichever method you use, the formula for each claim is:
This claim = value of work completed to date (including approved variations) − total of previous claims − retention or holdback (if the contract has one) + tax (GST/VAT/sales tax)
Retention, called retainage in the US and holdback in Canada, is a percentage the payer holds back from each claim until the job is finished or the defects period ends. Only deduct it if your contract says so, and record it so you can claim it back.
Progress claim template
A progress claim should let the payer check every number without ringing you. Copy this layout, top to bottom, and fill in the brackets:
- Heading: PROGRESS CLAIM No. [3]. Date: [date]. Claim period: [start] to [end].
- From: [your business name, address and tax number]. To: [customer or head contractor, address].
- Job: [job name and site address]. Contract or quote ref: [number]. Customer PO: [if given].
- Original contract price: $[ ]. Approved variations: $[ ]. Revised contract price: $[ ].
- Value of work completed to date: $[ ] ([ ]% of the revised price).
- Less previous claims: $[ ].
- Less retention ([ ]%, only if the contract has it): $[ ].
- This claim before tax: $[ ]. Tax: $[ ]. Total this claim: $[ ].
- Payment due: [date]. Pay by bank transfer to: [account name and bank details]. Reference: [claim number].
What to attach
- A breakdown by stage or line item, showing contract value, % complete, value to date, previously claimed and this claim.
- Approved variations listed separately, each with its reference and the date it was approved.
- Photos of the completed stages, dated.
- Any statement your contract or local law requires, such as a statement that the claim is made under a particular Act, which some places require.
Worked example: claim 2 on a $60,000 job
Say you have a renovation contracted at $60,000 before tax, billed by percentage complete on five line items. In claim 1 you billed demolition in full and half of the rough-in: $12,000. Here is claim 2 at the end of the next month.
| Line item | Contract value | % complete | Value to date | Previously claimed | This claim |
|---|---|---|---|---|---|
| Demolition and prep | $6,000 | 100% | $6,000 | $6,000 | $0 |
| Rough-in | $12,000 | 100% | $12,000 | $6,000 | $6,000 |
| Framing and lining | $15,000 | 60% | $9,000 | $0 | $9,000 |
| Fixtures and fit-out | $21,000 | 0% | $0 | $0 | $0 |
| Finishes and handover | $6,000 | 0% | $0 | $0 | $0 |
| Total | $60,000 | 45% | $27,000 | $12,000 | $15,000 |
Claim 2 is $15,000 plus tax. If the contract held back 5% retention on each claim, you would deduct $750 and claim $14,250 plus tax, and keep a running total of retention held so it can be claimed at the end.
Notice what the table does: the payer can see that the job is 45% done, that nothing is being claimed twice, and exactly which work this money is for. A claim laid out like this is hard to dispute, which is most of the reason it gets paid on time.
When should you send a progress claim?
Send a progress claim on the dates the contract sets, usually at the end of each stage or on the same day each month. If the contract is silent, agree a schedule in writing before work starts and stick to it.
- Stage-based claims suit homeowners: they can see the stage is finished, which makes the claim easy to approve.
- Monthly claims suit builders and commercial clients, who often run payments on a monthly cycle.
- Send each claim on the day it falls due. A late claim pushes your payment into the payer's next cycle.
- Send it to the person the contract names. A perfect claim sent to the wrong inbox waits.
Common progress claim mistakes that delay payment
- Claiming for work that is not finished, which gives the payer a reason to reject the whole claim.
- Mixing unapproved variations into the main claim. Claim them separately once approved.
- No breakdown, just a total. The payer cannot check it, so it waits.
- Previous claims that don't add up, because they were done in a spreadsheet someone overwrote.
- Missing the claim date or a required statement or form for your country or state.
- No due date or bank details on the claim.
Most of these come from building claims by hand at the end of the month. If the job already holds the contract price, variations and what has been billed, each claim is a percentage or an amount, not a reconstruction.
Progress claims are one part of getting paid on time. For terms, deposits and a follow-up schedule, see how to get paid faster (written for Australia and New Zealand, but the method works anywhere). And because every claim starts from the quote, it pays to write the quote with the stages in it.
Progress claim rules in Australia, New Zealand, the UK, the US and Canada
Many countries have laws that give construction businesses a right to be paid in stages and set time limits on payment. The rules depend on the country, often the state or province, and the type of contract. The notes below point to official sources; read the source before relying on any of it.
Australia
Each state and territory has its own security of payment law. In NSW, the government's security of payment page says contractors have a right to progress payments even where the contract is verbal or says they cannot claim them, and that claims can be made once a month unless the contract says otherwise. The Act has exemptions for work on a home the customer lives in: for an owner-occupier it doesn't cover electrical, plumbing, gas or air-conditioning work, or building work under $5,000 (NSW FAQ). It lists maximum payment due dates in business days and the time allowed to reply with a payment schedule. For home building work, NSW home building guidance requires a progress payment schedule in contracts over $20,000 and says payments should match the work carried out.
New Zealand
The Construction Contracts Act 2002 sets out a payment claim process for construction work, including how the payer responds if they dispute a claim. A payment claim under the Act has its own requirements, so check the official guidance on building.govt.nz before you rely on it. For general invoicing, business.govt.nz suggests splitting the total into smaller payments when work runs over a long time.
United Kingdom
The Housing Grants, Construction and Regeneration Act 1996 gives parties to a construction contract a right to stage or periodic payments unless the work is to last less than 45 days. It also requires a payment notice no later than five days after each payment due date, a pay less notice if the payer intends to pay less, and it allows the payee to suspend work after giving at least seven days' notice if the notified sum is not paid. Pay-when-paid clauses are generally ineffective. These payment rules do not apply to contracts with a residential occupier for work on their own home.
United States
Rules vary by state, and many states have their own prompt payment and lien laws, so check your state. On federal construction contracts, the FAR prompt payment clause says progress payments are due 14 days after the designated billing office receives a proper payment request, requires the contractor to pay subcontractors within 7 days of being paid, and allows subcontracts to provide for retainage.
Canada
Several provinces have their own prompt payment laws for construction, so check your province. For construction work on federal real property, the Federal Prompt Payment for Construction Work Act requires the contractor to submit a proper invoice monthly or as the contract specifies, and requires payment no later than 28 days after the proper invoice is received (s.9(2)). The payer can withhold some or all of it only by giving a notice of non-payment within 21 days (s.9(3)). Subcontractors further down the chain get their own deadlines.
This is general information, not legal advice.
Questions
What is the difference between a progress claim and an invoice?
A progress claim bills part of a job based on the work done so far, and each claim builds on the ones before it. An invoice usually bills a whole job or a fixed amount. Many progress claims are issued as tax invoices too, but they carry the running totals that show how much of the contract has been billed.
How often can you make a progress claim?
As often as your contract allows, usually at each stage or once a month. Some laws set a default where the contract is silent; in NSW, for example, the official guidance says claims can be made once a month unless the contract says otherwise. Check the rules where you work.
Can I claim for materials delivered to site but not installed?
Only if your contract allows it. Some contracts let you claim for materials on site, often with proof of ownership or insurance. If it isn't in the contract, claim the materials when they are installed.
What happens if the client disputes part of a progress claim?
Ask them to say in writing which items they dispute and why, and get the undisputed amount paid on time. Many payment laws require the payer to respond with a payment schedule or pay less notice within a set time. Check the official rules for your country or state before you escalate.