How to get paid faster as a tradie, without chasing and without card fees

By Carlos B., Founder, Always On Tradie8 min read

How to get paid faster as a tradie: agree the terms before you start, take a deposit, bill big jobs in stages, send the invoice from the job the day it's finished, and make bank transfer the obvious way to pay. No card reader, no payment links, and no chasing for weeks.

The fastest way for a tradie to get paid is to remove every reason for the customer to wait. That means terms they agreed to before work started, an invoice that arrives the same day the job finishes, bank details they can copy straight into their banking app, and a polite reminder on a set day if the money doesn't land.

None of that needs a card reader or a payment link. It needs the paperwork done in the right order. This post walks through each step, with wording you can copy, a worked example for a bigger job, a follow-up schedule, and a short section on the payment rules for trades in Australia and New Zealand.

Why do tradies get paid late?

Many late payments can be prevented by the business that's owed the money. The invoice goes out a week after the job, the terms were never agreed, or the invoice is missing something the customer needs before they can pay it.

  • The invoice is written on Sunday night from a pile of dockets, days after the job.
  • Payment terms were never mentioned on the quote (or estimate), so the customer picks their own.
  • The invoice has no due date, or says "14 days" without saying 14 days from when.
  • Bank details or a payment reference are missing, so the customer has to ask.
  • A big job is billed in one lump at the end, so the customer has to find the whole amount at once.
  • Nobody follows up, so a forgotten invoice stays forgotten.

Each of these is fixable without changing how you price or who you work for.

Set the payment terms before you start

Payment terms work best when they're on the quote (or estimate) the customer accepts, so paying on time is something they agreed to, not something you're asking for later. Australia's business.gov.au notes that payment terms form part of a sales contract, and recommends putting them on invoices and contracts.

Keep the terms short enough that a customer reads them. Here is wording you can adapt:

Payment terms: A deposit of [X]% is due on acceptance and confirms your booking. For jobs over [amount], we invoice in stages as set out below. Final invoice is due 7 days from the invoice date. Payment by bank transfer to the account on the invoice, using the invoice number as the reference.

Short terms get paid sooner

Service NSW's tips for getting paid faster suggest shorter terms, such as 7 days where possible, and issuing invoices immediately after completing a job. For homeowners and small jobs, 7 days is normal and easy to explain. For builders and head contractors, the contract usually sets the terms, and the rules further down may apply.

Should you take a deposit, and how much?

Take a deposit when you're buying materials for a specific customer or holding days in your schedule for them. A deposit covers your costs if the job falls over and shows the customer is committed. On residential building work, check your state's limits first: in NSW, for example, the maximum deposit under home building law is 10 percent.

A starting point for deposits. Check the rules for your state or region and your contract.
Type of jobDepositHow the rest is billed
Small service job or call-outNoneInvoice on the day, 7-day terms
Job with materials ordered for this customerEnough to cover the materials, within any legal capBalance on completion
Residential building work in NSWNo more than 10%Progress payments that match work done
Job running over several weeksDeposit, within any legal capProgress claims at agreed stages
Work for a builder or head contractorAs the contract saysProgress claims, often monthly

Invoice from the job, the same day

The invoice that goes out the day the job is finished gets paid first, because the customer has just seen the work and still has the job in their head. New Zealand's business.govt.nz advice is the same: send the invoice as soon as the work is finished, while the value of your work is still fresh.

Same-day invoicing only works if the job already holds what goes on the invoice. If labour and materials are recorded on the job as the work happens, the invoice is a check and a send, not an evening of reading dockets.

  1. Record labour and materials against the job as you go, not at the end of the week.
  2. When the job is marked complete, check the charges against the quote and any variations.
  3. Send the invoice before you leave site or by the end of the same day.
  4. Send it from your business email, so replies and questions land with you.

What to put on the invoice

  • Your business name and ABN (Australia) or GST number (New Zealand) if you are registered.
  • The customer's name and the job address.
  • Invoice number and invoice date.
  • What you did, in plain words, with the quote number and any variations.
  • The amount, with GST shown.
  • A due date written as a date, such as "Due 20 November", not "14 days".
  • Bank details: account name, BSB and account number in Australia, or the full bank account number in New Zealand.
  • The reference to use, which should be the invoice number.

A customer who can copy the account number and reference straight into their banking app has no reason to wait. One who has to ring and ask now has a reason to do it next week.

How do progress claims help you get paid faster?

Progress claims get you paid during a long job instead of after it, so you're never carrying weeks of wages and materials on your own account. You agree the stages up front, then claim each one as it's reached.

Say you quote a renovation at $24,000 (AUD or NZD) over four weeks. Billed in one go, you wait a month or more for any money. Billed in stages, it looks like this:

Worked example: a $24,000 job billed in stages. Figures are illustrative.
StageWhen it is claimedClaimClaimed to date
Deposit (10%)On acceptance$2,400$2,400
Stage 1: strip-out and rough-inEnd of week 1$7,200$9,600
Stage 2: lining, waterproofing, fixtures on siteEnd of week 3$9,600$19,200
Final: fit-off and handoverOn completion$4,800$24,000

Each stage should match work actually done, which is what customers expect and, for NSW home building contracts, what the official guidance asks for. For the full method, with a template and how to work out each claim, see progress claims explained.

Why bank transfer works without card fees

Bank transfer is a payment method most customers already use for bills, and it doesn't come with a card merchant fee taken off your invoice. The catch is that it relies on the customer doing it, so your job is to make it take less than a minute.

  • Print the bank details on every invoice and progress claim, in the same place every time.
  • Ask for the invoice number as the reference, so you can match the payment without guessing.
  • Put the amount due and due date at the top, not buried under the line items.
  • Send a PDF, so the details survive being forwarded to a partner or an accounts team.

A follow-up schedule that does not feel like chasing

Following up feels like chasing when it's irregular and annoyed. On a fixed schedule it's just admin, and an overdue invoice is often just a forgotten one. business.govt.nz suggests a clear process such as an email reminder two business days after the due date, followed by a phone call if there's no response after a week.

A follow-up schedule for a 7-day invoice. Adjust to your terms.
WhenWhat you sendTone
Day 0Invoice, same day as the jobThanks for the work
Due date + 2 business daysShort email reminder with the invoice attachedFriendly, assume it was missed
Due date + 7 daysPhone call, then an email confirming what was saidDirect, ask when it will be paid
Due date + 14 daysWritten notice stating the amount, due date and next stepFirm and factual
After thatYour next step: a letter of demand, debt collection or the formal process for your tradeFormal
Hi [name], just a reminder that invoice [number] for [job] was due on [date]. I have attached it again in case it went astray. Bank details and the reference are on the invoice. Thanks, [your name]
Hi [name], invoice [number] for $[amount] is now [X] days overdue. Can you let me know today when it will be paid? If there's a problem with the work or the invoice, tell me and I'll sort it out.

Keep early reminders short. An overdue invoice is usually a forgotten one, and a polite nudge gets it paid without souring a customer you'll want again.

Payment rules for trades in Australia and New Zealand

Both countries have laws that give construction businesses extra rights to be paid, but the details depend on where you work and who you work for. Use this as a pointer to the official sources, not a summary of the law.

Australia

Each state and territory has its own security of payment law for construction work. In NSW, the government's security of payment page says contractors have a right to progress payments even if the contract is verbal or says they can't claim them, and that claims can be made once a month unless the contract says otherwise. The Act has exemptions for work on a home the customer lives in: for an owner-occupier it doesn't cover electrical, plumbing, gas or air-conditioning work, or building work under $5,000 (NSW FAQ). The page also lists maximum due dates, counted in business days from when the claim is made, and the time the other party has to reply with a payment schedule if they won't pay the full amount.

For work on homes, NSW also has home building rules: a written contract over $5,000 (including GST), a 10 percent cap on deposits, and a progress payment schedule in contracts over $20,000, with payments that match work done. Other states have their own versions, so check your state regulator before you set your terms.

New Zealand

New Zealand's Construction Contracts Act 2002 sets out a formal payment claim process for construction work, including how the other party responds if they dispute the amount. A payment claim has its own requirements, so if you want to rely on the Act, read the Act and the official guidance on building.govt.nz before you send one rather than assuming a normal invoice will do. For everyday invoicing, business.govt.nz recommends clear due dates and payment terms on every invoice, and splitting the total into smaller payments for work done over a long time.

This is general information, not legal advice.

The short version

  1. Put payment terms on the quote, including any deposit and stages.
  2. Take a deposit when you are buying materials or holding days, within the rules for your area.
  3. Bill long jobs with progress claims that match the work done.
  4. Send the invoice the day the job is finished, with a due date and bank details.
  5. Follow up on a fixed schedule: email, call, written notice.

Most of the delay in getting paid is admin that happens too late. If you want to see where the rest of the office hours go, read where tradie admin time goes.

Questions

What payment terms should a tradie use?

For homeowners and small jobs, 7 days from the invoice date is common and easy to explain. For bigger jobs, combine a deposit with progress claims at agreed stages. Work for builders usually follows the contract's terms, and security of payment or construction contract laws may apply.

Do I need to accept card payments to get paid faster?

No. Most of the delay comes from late or unclear invoices, not the payment method. An invoice sent the same day, with a due date, bank details and a reference, gets paid by bank transfer without any card fees.

How much deposit can a tradie ask for?

It depends on the work and where you are. For residential building work in NSW, the maximum deposit under home building law is 10 percent. Check the rules for your state or for New Zealand before setting a deposit on home building work.

What should I do if a customer won't pay?

Follow up in writing two business days after the due date, then call, then send a written notice with the amount and your next step. If that fails, look at a letter of demand, debt collection or, for construction work, the formal payment claim process for your state or for New Zealand.